Hanoi to consider petitioning for compensation of US$81 million
Regarding the compensation value of US$81 million requested by the contractor, the leaders of the Hanoi Urban Railway Management Board denied that the loss was incurred by the delayed land clearance and disbursement.
The Hanoi Urban Railway Management Board said that they will discuss with Nhon - Hanoi Railway project’s contractor about the compensation of US$81 million due to delayed clearance and disbursement.
At the meeting with leaders of the Hanoi People's Committee, Deputy Director of Nhon - Hanoi Railway project Romano Mauro Ruggero requested the compensation.
Deputy Director of the Hanoi Urban Railway Management Board Le Trung Hieu said the contractor has to demonstrate the evidence showing the responsibilities of the investor for the contractor’s loss. The contractor was also asked explain the causes incurring the loss under Vietnamese regulations.
As a rule, the two sides will have a negotiation time of 84 days. In the process, the contractor keeps executing the project and does nothing to harm its progress.
Regarding the compensation value of US$81 million requested by the contractor, the leaders of the Hanoi Urban Railway Management Board denied that the loss was incurred by the delayed land clearance and disbursement, and rejected to compensate previously.
Currently, the investor is focusing on solving problems as soon as possible to complete the clearance for the remaining four underground stations of the project, so that the contractor can continue to work.
Nhon - Hanoi Railway project. Photo: Kinhtedothi.vn
|
Deputy Director of the Hanoi Urban Railway Management Board Le Trung Hieu said the contractor has to demonstrate the evidence showing the responsibilities of the investor for the contractor’s loss. The contractor was also asked explain the causes incurring the loss under Vietnamese regulations.
As a rule, the two sides will have a negotiation time of 84 days. In the process, the contractor keeps executing the project and does nothing to harm its progress.
Regarding the compensation value of US$81 million requested by the contractor, the leaders of the Hanoi Urban Railway Management Board denied that the loss was incurred by the delayed land clearance and disbursement, and rejected to compensate previously.
Currently, the investor is focusing on solving problems as soon as possible to complete the clearance for the remaining four underground stations of the project, so that the contractor can continue to work.
20:51, 2025/01/22
Vietnam-Singapore Friendship Association launched in Hanoi to strengthen bilateral ties
The congress adopted the association's charter and outlined its strategic objectives.
22:56, 2025/01/21
Hanoi, HCMC to submit metro plans to National Assembly in February: Deputy PM
The resolution aims to speed up the development of the urban railways in Hanoi and Ho Chi Minh City.
15:18, 2025/01/21
Hanoi integrates administrative procedures into national public service portal
The entire process is digitized and shared among agencies at all levels, saving time and ensuring transparency.
21:53, 2025/01/19
2025 spring book fair opens to boost reading in Hanoi
The 2025 Spring Book Fair promises to establish itself as an annual event that celebrates the importance of books and knowledge.
20:49, 2025/01/19
Traditional essence in Hanoi's Old Quarter Tet celebration program
The activities include worshiping rituals, calligraphy, and folk music.
19:47, 2025/01/19
Annual Tet flower market opens in Hoan Kiem District
With many iterations over the years, the traditional market continues to hold its own appeal, combining the past and traditional values with the present and modern world.
- Thousands of people rejoice Hanoi International Light Festival 2025
- HUFO looks back at 2024 with impressive results
- More than 2,000 drones paint Hanoi's landmarks in New Year's skies
- Hanoi accelerates completion of Ring Road No. 4 service roads in 2025
- Hanoi’s greater autonomy under Capital Law unlocks new growth opportunities
- Exhibition combines young creativity with Phu Xuyen’s traditional crafts