WORDS ON THE STREET 70th anniversary of Hanoi's Liberation Day Vietnam - Asia 2023 Smart City Summit Hanoi celebrates 15 years of administrative boundary adjustment 12th Vietnam-France decentrialized cooperation conference 31st Sea Games - Vietnam 2021 Covid-19 Pandemic
Home / Economy / Construction
Hanoi pushes for completion of ring road networks
Ngoc Mai 12:17, 2024/06/22
Although considerable resources have been invested, only 132 km (46.33%) of the planned 285 km ring roads have been constructed.

For many years, Hanoi has devoted significant resources to gradually completing and fully connecting its ring road system, but much remains to be done.

 The elevated part of the Ring Road No.2 in Hanoi. Photo: Pham Hung/The Hanoi Times

Despite significant investment over the years, Hanoi's ring road network remains incomplete, with only 46% finished according to the plan. In response, the city plans to phase investments to ensure feasibility. Contractors have been required to be prepared with resources and manpower to accelerate the progress of eligible projects.

One year after the start of work, Hanoi's Ring Road 4 project has seen considerable progress. Nguyen Chi Cuong, Director of Hanoi's Transport Construction Investment Project Management Board, stated that this national key project has been actively pursued by all stakeholders since construction began in June 2023.

“The project is currently on track,” said Cuong.

To build the service roads to the Ring Road in Hanoi, contractors have mobilized around 600 engineers and workers, along with hundreds of machines, across 32 construction sites. The 13 km section north of the Red River is expected to be completed by the end of 2024, while the 19 km section in Hoai Duc District is scheduled to be finished by mid-2025. Work on other sections is progressing at a similar pace. For Ring Road 4 itself,  built under the PPP (public-private partnership), steps are being taken to complete investment procedures and select an investor by the end of Q3 2024.

At the site of Vinaconex's 23-kilometer Ring Road 4 service road through Dan Phuong and Hoai Duc districts, project manager Nguyen Hoang Hai reported that taking advantage of favorable weather conditions, 23 construction teams with 140 machines and nearly 340 workers are working simultaneously on roads and bridges to speed up the project. In early October 2022, Hanoi began construction of an underpass at the Kim Dong - Giai Phong intersection on Ring Road 2.5 in Hoang Mai District. After over a year and a half, significant portions of this 460-meter-long, four-lane underpass have been completed. Key works such as the Dam Hong side tunnel and the Kim Dong road extension are well underway.

Ho Duc Phuc, Director of the Kim Dong Underpass Project for Cienco4, indicated that the project is divided into three zones and has reached over 45% completion. All resources are being mobilized to meet the project deadline.

The Ring Road 1 project between Hoang Cau and Voi Phuc, which stretches  2,274 meters through the Ba Dinh and Dong Da districts, has been delayed due to land clearance issues. Vice Director of the Hanoi Project Management Unit of Civil and Industrial Projects Do Viet Hung said the project is expected to finish in 2024, but delays in land clearance have extended the timeline to Q1 2025.

“Efforts are underway to accelerate land clearance and select construction contractors,” Hung added.

 Construction of Ring Road No.4 in Hanoi. Photo: Pham Cong/The Hanoi Times
Find a workable plan
According to Hanoi's Transport Development Plan for 2030, with a vision for 2050 approved by the Prime Minister, Hanoi will have seven ring roads, including five main ones (Ring Roads 1, 2, 3, 4, 5) and two auxiliary ones (Ring Roads 2.5 and 3.5). These roads are crucial to the city's transportation network and overall development.
Although considerable resources have been invested, only 132.26 km (46.33%) of the planned 285.46 km ring roads have been completed. A further 20.51 km (7.18%) are under construction, 83.26 km (29.16%) are in the planning stage, and 49.43 km (17.33%) have not yet been studied for project development.

Specific challenges include the significant investment required, particularly for the 83.26 km currently being planned for five sections of Ring Road 3.5 and Ring Road 4 in Hanoi, which will require approximately VND53.5 trillion (US$2.1 billion).

Vice Director of Hanoi Transport Department Tran Huu Bao pointed out that land clearance and resettlement in densely populated areas also pose significant challenges, affecting project schedules and social stability.

"This remains a major factor in delaying the construction of the ring road network, which has reached only 46.33% completion so far," said Bao.

According to Bao, to address these challenges and complete the ring road system, Hanoi's Department of Transport has proposed phased investments for the remaining segments. For Ring Road 1's Hoang Cau - Voi Phuc segment, the plan is to first complete key intersections by 2025, with the remaining components to follow in subsequent phases. For Ring Road 2, the department proposes completing the Nga Tu So - Cau Giay segment, including the elevated road, by 2026-2030. For the remaining 14 km of Ring Road 3, the city plans to include this segment in the 2021-2025 medium-term public investment plan, eventually completing the entire ring road network of Hanoi, he noted.

RELATED NEWS
TAG: vietnam ring road network Hanoi transport infrastructure hanoi project development
Other news
18:59, 2024/09/05
9 more housing projects approved for commercial launch in Hanoi
By 2025, Hanoi is projected to complete 26 projects with nearly 9,900 units.
17:19, 2024/08/15
PM wants to finish 500kV transmission line by Independence Day
This project has a transmission capacity of around 2,400 MW and will enhance electricity supply to the northern region from 2025.
20:35, 2024/08/10
Vietnam earmarks US$80 million to connect to Chinese railways
The project, once completed, would help facilitate cargo transportation between Vietnam and China.
18:44, 2024/07/13
New Housing Law to lift legal barriers to renovating old apartments in Hanoi
The 2023 Housing Law introduces several important changes to address these issues.
13:50, 2024/07/11
Long-term solutions needed for organizing Hanoi’s rural architectural spaces
Traditional rural architectural treasures like stilt dwellings and communal houses are being commercialized and relocated to urban areas, undermining their original cultural and architectural integrity.
14:19, 2024/07/09
Amended Capital Law to help Hanoi realize Red River zoning plan
It is critical to put available riverbank land to good use in order to enhance landscape, cultural, economic, and tourism values while ensuring flood and disaster prevention.