Time for construction license considerably reduced
Prime Minister Nguyen Xuan Phuc has issued a directive on the accelerated implementation of measures to shorten time for granting construction licences and relevant procedures.
Time for construction license considerably reduced
|
The procedures to appraise construction designs, technical designs and to grant construction permits will be reduced to no longer than 63 days, 19 days fewer than the figure evaluated by the World Bank in 2017.
The time limit for the appraisal of fire and explosion prevention and fighting measures will be reduced to 20 days, a reduction of 10 days.
Meanwhile, the time limit to handle procedures to supply electricity and water and connect water drainage systems will be 7 days instead of 14 days as previously.
The procedures to handle the registration of land and property on land, to grant approval for land use, homeownership and ownership of property on land are also asked to be cut by 10 days to no more than 20 days.
The PM requested that ministries, sectors and localities to enhance the use of IT, improve the efficiency of the single-window mechanism and promote the use of online public services.
State agencies involved in the process were also asked to increase cooperation to simultaneously carry out related administrative procedures to speed up the process.
The Ministry of Construction is responsible for monitoring the implementation of the PM’s directive and reporting to the PM if problems arise.
22:20, 2024/12/27
Hanoi to rent nearly 900 sidewalks next year
The number of streets approved by the city's authorities for on-street parking is 234 as of December 16, 2024.
15:13, 2024/12/27
Quoc Oai District breaks ground on industrial clusters
The industrial clusters have a total investment of US$35.7 million.
11:03, 2024/12/23
Stronger decentralization key to Hanoi's urban railway ambitions
With transformative policies that include amendments to the Capital Law and specific proposals for urban rail projects, Hanoi is committed to achieving its intended goals for urban rail development.
23:20, 2024/12/14
Prime Minister urges acceleration of social housing projects
Hanoi focuses on expediting housing projects, overcoming administrative hurdles, and promoting collaboration between public and private sectors to meet the increasing demand for affordable housing.
15:23, 2024/12/12
Hanoi Forum explores innovative solutions for sustainable urban development
The forum, hosted by the Economic & Urban Newspaper, is designed to inspire innovative ideas and solutions and foster collaboration for a sustainable urban future.
15:44, 2024/12/10
Prime Minister urges Chinese companies to collaborate on infrastructure projects
Trade between Vietnam and China has quadrupled in the last decade.
- Lao Cai – Hanoi – Haiphong railway section to be built in 2027
- New supply to boost Hanoi retail property market
- Vietnam, China cross-border railway project to start construction in 2025
- Hanoi approves 14 residential projects amid market challenges
- Prime Minister urges quick construction of National Exhibition Center
- Hoa Lac Park aims to become “a high-tech hub”