Special mechanism for Hanoi’s Cat Linh-Ha Dong railway approved
The Prime Minister has approved a special mechanism to complete Hanoi’s Cat Linh-Ha Dong urban railway project in an effort to address numerous delays and cost overruns.
The Cat Linh-Ha Dong urban railway project was supposed to be completed by the end of this year. However, only 74% of the project has been finished since it broke ground in September 2010, according to the project’s management unit.
The investment in the project increased from a projected 542 million USD in 2008 to 892 million USD in 2014.
According to the special mechanism, proposed by the Ministry of Transport, the main contractor (China Railway Sixth Group) will be authorised to make decisions, especially on buying equipment, without having to seek time-consuming permission from State authorities. However, the contractor must ensure that prices do not exceed those set out in the signed contract.
The investment in the project increased from a projected 542 million USD in 2008 to 892 million USD in 2014.
According to the special mechanism, proposed by the Ministry of Transport, the main contractor (China Railway Sixth Group) will be authorised to make decisions, especially on buying equipment, without having to seek time-consuming permission from State authorities. However, the contractor must ensure that prices do not exceed those set out in the signed contract.
Regarding the selection of foreign contractors for safety assessments, the Prime Minister has agreed in principle that contractors will be chosen in accordance with Article 26 of the Law on Bidding, ensuring that selected contractors are qualified, have adequate experience and meet the requirements of the tender package.
On additional loans for the project, the Ministry of Planning and Investment and the Ministry of Finance were urged to promptly work with the Chinese side on reaching agreement on supplement preferential loans for the project.
The Prime Minister required the Ministry of Transport to review the preparation and implementation of the project as a lesson for the next steps of the project and other projects to ensure the efficiency, quality assurance and construction progress.
22:21, 2025/01/15
Hanoi to increase supply of essential goods by 30%-35% for Tet
Authorities in Hanoi planned to prevent price hikes during the national holiday by stocking up on goods and ensuring food supplies.
22:39, 2025/01/01
Hanoi works to ensure merry Tet
The move aims to make the best preparations for the traditional Tet celebrations.
17:37, 2024/12/30
Channel needed to expand Hanoi's OCOP products: Experts
Hanoi has devised a plan to boost the sale of OCOP products by creating OCOP venues associated with rural tourism and craft village visits in the city.
21:24, 2024/12/28
Rising Like Bamboo: Vietnamese Identity on the Global Stage
The Vietnam International Awards 2024 brings together outstanding individuals, compassionate hearts, and promising young talents, all united by a common goal: to connect and spread the positive values of the Vietnamese community worldwide.
15:55, 2024/12/17
Circular economy requires solid waste management in Hanoi
Synchronized procedures and regulations for the classification, collection, treatment, and recycling of household solid waste are necessary to support the circular economy in Hanoi.
14:18, 2024/12/15
Hanoi's top priority is to keep students safe while traveling
The local government has set up teams of volunteers to control traffic at school entrances while maintaining the Safe School Gates model throughout the city.
- Hanoi pioneers in using interoperable smart cards for public transport
- Hanoi to establish customer service hub for administrative reform
- Hanoi tops country for blood donation in 2024
- Hanoi disseminates safe eating practices
- Teaching Vietnamese: Starting with emotional connections
- Hanoi upholds great national unity bloc