WORDS ON THE STREET 70th anniversary of Hanoi's Liberation Day Vietnam - Asia 2023 Smart City Summit Hanoi celebrates 15 years of administrative boundary adjustment 12th Vietnam-France decentrialized cooperation conference 31st Sea Games - Vietnam 2021 Covid-19 Pandemic
Home / Economy / Construction
Hanoi Mayor urges greater responsibilities in public investment
Ngoc Mai 11:38, 2023/07/19
Disbursement progress in the year's first half was below expectations at 33.9% of the target.

The leaders of districts, wards, departments, and project management boards bear the responsibility of ensuring timely disbursement progress, with their performance being considered a criterion for quarterly and annual evaluations.

 Hanoi's Mayor Tran Sy Thanh at the meeting. Photo: The Hanoi Times

Chairman of the Hanoi People's Committee Tran Sy Thanh stressed this view at a meeting to discuss the city's public investment works in the second quarter on July 18.

A Department of Planning and Investment report showed that the disbursement of public investment funds in Hanoi in the first half of 2023 amounted to VND15.93 trillion (US$673.78 million), reaching 33.9% of the planned target.

Of this, VND9 trillion (US$380.6 million) was allocated to public investment projects at the city level, reaching 34.8% of the plan, while the district budget accounted for VND6.84 trillion (US$289.3 million), reaching 34.4% of the plan.

However, the city's overall disbursement results fell short of both plans, which were set at 40-45%.

As of June 2023, 105 projects under the 2023 capital plan were facing various problems, the department said.

Among them were 73 projects facing delays due to site clearance issues, 11 facing difficulties with grave relocation, and 16 facing resettlement challenges, among others.

In addition, 21 projects in the 2022 capital plan had ongoing problems with site clearance, raw material prices, environmental impact assessment, asset liquidation, and investment level adjustment.

 Construction of Vinh Tuy Bridge Phase 2. Photo: Pham Hung/The Hanoi Times

Despite achieving a disbursement rate of nearly 34%, which is higher than the same period in 2022 (nearly 24%) and higher than the national average, Deputy Chairman of the City People's Committee Duong Duc Tuan expressed concern about the prospects of failing to reach 100% disbursement rate by year-end, as numerous difficulties and obstacles remain.

While some units have relatively high disbursement rates, such as Tay Ho (78.7%), My Duc (77.6%), and Long Bien (63%), several others are significantly lower, including Hoang Mai (24%), Thanh Xuan (23.2%), Son Tay (12.1%), Cau Giay (3.6%), and the Thang Long-Hanoi Heritage Conservation Center (0.1%).

Public investment has been a key task for Hanoi in an effort to boost socio-economic development, especially since the capital's administrative boundary expansion 15 years ago

Tuan called on all city units to make greater efforts in the remaining months of the year to strengthen their responsibilities, with a special focus on managing disbursement and addressing difficulties and obstacles to ensure effective plan implementation.

In his concluding remarks, Tran Sy Thanh, Chairman of the Hanoi People's Committee, praised and highly appreciated the units' dedicated participation in the disbursement of public investment funds.

However, he also acknowledged the existing coordination problems between units and departments and emphasized the need to promptly identify and address these problems. The Chairman emphasized the critical role of investors in improving project efficiency and disbursement, especially in the critical phases.

Regarding project implementation and disbursement, Thanh emphasized that the site clearance process, especially for transport projects, remains a weak point.

He ordered the compilation of statistics on projects funded by the city, central government, and mixed capital with land problems.

"These statistics will be reported to the municipal Party Standing Committee for leadership and guidance in coordination with the districts," he noted.

Stressing the importance of 2023 as a critical year in the implementation of the five-year socio-economic development plan 2020-2025, Thanh emphasized the need for units to be proactive and involved at all stages, from investment policies to investment decisions.

"Leaders of district-level People's Committees, department heads, and project management boards are responsible for the progress of disbursement, which will be considered a criterion for quarterly and annual performance evaluations," Thanh said.

RELATED NEWS
TAG: Vietnam news Hanoi news hanoi public investment hanoi disbursement public funds 2023 hanoi tran sy thanh 2023
Other news
18:30, 2024/11/13
New supply to boost Hanoi retail property market
Hanoi's retail property market continues to show strong growth potential.
11:35, 2024/11/07
Vietnam, China cross-border railway project to start construction in 2025
The project will serve as a vital railway link between Vietnam and China, advancing the Belt and Road Initiative.
20:56, 2024/11/04
Hanoi approves 14 residential projects amid market challenges
The fourth quarter would see increasing supply of new apartments, with around 9,700 units to get launched.
11:34, 2024/10/26
Prime Minister urges quick construction of National Exhibition Center
Once completed, the center is expected to be a venue for major international and regional events.
20:37, 2024/10/16
Hoa Lac Park aims to become “a high-tech hub”
The Hoa Lac Hi-tech Park is being built as an open model and will serve as the core for the transformation of Hanoi into the country's leading hub for innovation.
21:22, 2024/10/01
Hanoi to build a new biotech high-tech park
The HaBiotech is designed to engage in high-tech activities that align with global trends and Vietnam's strategic policies for high-tech development, with a particular focus on biotechnology.