Cat Linh-Ha Dong Railway doubled manpower to ensure progress
Tuan Minh 11:39, 2018/04/06
To ensure the completion as required by the Ministry of Transport, the EPC contractor of Cat Linh - Ha Dong Railway project doubled the manpower for executing the project.
 
Cat Linh-Ha Dong Railway
Cat Linh-Ha Dong Railway
The equipment installation of Hanoi’s Cat Linh-Ha Dong elevated railway line is expected to be done by May 30 and basic construction of its stations will be completed a month later, according to the contractor.

The railway is set to be put into commercial operation in December 2018.

To date, 95 percent of the basic construction of the railway line has been completed while 60 percent of the equipment is ready for installation.

The installation of lighting systems, elevators, ventilation, as well as drainage systems and fire prevention is underway. More than 600 workers are taking part in the project, double the figure before January 2018.

The Cat Linh-Ha Dong elevated railway project with 12 stations and one depot area has investment of 868 million USD sourced by official development assistance loans from China. The railway project has 12 trains, including 48 carriages. Each train with four carriages can carry 1,200 passengers.

The 13 kilometre railway is set to operate trains with carrier frequency of every two minutes and a maximum speed of 80 kilometres per hour.

Construction on the project was meant to start in 2008 but was delayed until October 2011. The line was originally supposed to start running in November 2013. 
Other news
15:34, 2024/04/16
Hanoi to build 14 urban railway lines
The city will replace the Kim Ma – Yen Nghia Bus Rapid Transit (BRT) line with an urban railway.
15:38, 2024/03/27
Hanoi People’s Council set to ratify capital planning until 2045 in late March
The planning project is expected to not only help alleviate population density in the inner city area but also serve as a driving force for the sustainable development of the capital city, namely the city-within-a-city model.
05:08, 2024/03/08
Hanoi aims to complete An Duong – Thanh Nien overpass in June
The project is important for easing traffic congestion in the capital.
17:14, 2024/02/29
Hanoi nears start of construction on US$660-million Tran Hung Dao Bridge project
Construction is scheduled to take two years, with an anticipated completion date in 2027.
22:37, 2024/02/27
Hanoi creates favorable conditions for Turkish businesses
Major Turkish conglomerate IC & Holding expressed its desire to invest in large-scale transport infrastructure projects in Hanoi.
07:27, 2024/02/27
Transforming Thien Quang Lake: Central hub for community connectivity
The objective is to enhance the urban landscape and upgrade existing public amenities, creating versatile cultural and artistic spaces with modern facilities to improve the quality of life and attract visitors.