Lack of preparation behind slow disbursement of public funds: Deputy PM
Hai Yen 21:39, 2022/01/19
Last year, Vietnam’s disbursed amount of public funds stood at 77.3% of the year’s estimate, lower than in the same period of the previous year when 82.66% of the year’s allocations were disbursed.

Slow disbursement of public funds has been a persistent issue for many years, for which a lack of preparation from the investment procedures to site clearance has been one of the main issues.

 Deputy Prime Minister Le Minh Khai at the discussion. Source: quochoi.vn

Deputy Prime Minister Le Minh Khai gave the remarks at a discussion session held by the Standing Committee of the National Assembly (NA) on public investment in the 2021-2025 period today [January 19].

Last year, Vietnam’s disbursed amount of public funds stood at 77.3% of the year’s estimate, 6% lower than that of the same period last year. Upon breaking down, the disbursement of domestic funds reached 84% of the plan, and that of foreign sources hit just 26.77%.

Statistics from the Ministry of Finance (MoF) revealed only 20 out of 63 provinces/cities and seven ministries have spent over 80% of their budget allocations, while 30 from the total 50 ministries/ministerial level-agencies and 16 provinces/cities recorded the figure below 65%.

For 2022 and the subsequent years, Khai said the Government is committed to ensuring flexible management of both mid-term public investment funds and the economic recovery program.

“Each project under the mid-term public investment plan and the recovery program would be reported to the Standing Committee for greater efficiency in disbursement,” Khai noted.

On this issue, Deputy Auditor General Nguyen Tuan Anh urged the Government to take drastic action to improve the disbursement rate, including a clear deadline for completion with severe penalties for those failing to meet it.

NA Chairman Vuong Dinh Hue noted a key factor for efficient state budget allocation is thorough preparation in the pre-investment process.

A Government report suggested it plans to allocate VND824.7 trillion ($36.3 billion) in mid-term public investment plan 2021-2025 for ministries, ministerial-level agencies, and localities.

So far, nearly VND640 trillion ($28.2 billion) is subject to the Standing Committee’s approval before being allocated for disbursement.

Vice Minister of Planning and Investment Tran Quoc Phuong said the ministry is prepared to speed up investment procedures for public projects to avoid possible delay, as well as take steps to supervise the implementation process.

As of December 27, 2021, Hanoi disbursed a total of VND25.38 trillion ($1.11 billion) of public funds, equivalent to 61% of the target set by Prime Minister Pham Minh Chinh.

RELATED NEWS
TAG: Vietnam public investment Covid-19 Vietnam disbursement public funds vietnam
Other news
23:20, 2024/12/14
Prime Minister urges acceleration of social housing projects
Hanoi focuses on expediting housing projects, overcoming administrative hurdles, and promoting collaboration between public and private sectors to meet the increasing demand for affordable housing.
15:23, 2024/12/12
Hanoi Forum explores innovative solutions for sustainable urban development
The forum, hosted by the Economic & Urban Newspaper, is designed to inspire innovative ideas and solutions and foster collaboration for a sustainable urban future.
15:44, 2024/12/10
Prime Minister urges Chinese companies to collaborate on infrastructure projects
Trade between Vietnam and China has quadrupled in the last decade.
16:00, 2024/11/19
Lao Cai – Hanoi – Haiphong railway section to be built in 2027
The Lao Cai - Hanoi - Hai Phong railway will begin at the junction with the Chinese railway in Lao Cai City, Lao Cai Province, and end at Lach Huyen Port in Haiphong.
18:30, 2024/11/13
New supply to boost Hanoi retail property market
Hanoi's retail property market continues to show strong growth potential.
11:35, 2024/11/07
Vietnam, China cross-border railway project to start construction in 2025
The project will serve as a vital railway link between Vietnam and China, advancing the Belt and Road Initiative.