Changes needed for PDP VIII to ensure viable power supply: Trade Ministry
Ngoc Mai 14:29, 2024/09/07
The Ministry of Industry and Trade (MoIT) said it is planning to revise the Power Development Plan (PDP VIII), a little over 15 months after its approval, to ensure a feasible energy supply.

The Ministry of Industry and Trade (MoIT) is seeking feedback from government entities and relevant stakeholders on a draft report to the Prime Minister on adjustments to the National Power Plan until 2030 (PDP VIII), which was approved in May.

 EVN's workers checking the transmission line in Vietnam's central region. Photo: Hoang Anh/The Hanoi Times

According to the MoIT, the electricity supply from 2025 to 2030 faces significant challenges, with potential shortfalls in peak capacity during dry seasons. Additionally, the approved power sources are not meeting the planned schedules, raising concerns about future energy shortages. Specifically, the growth rate of commercial electricity nationwide from 2021-2025 is projected at 9.08%, but in the first seven months of this year, demand surged by 13.7%, much higher than the   sub-5% growth in the previous period.

As a result, it seems unlikely that the targeted growth rate for commercial electricity will be achieved by 2025. The MoIT emphasizes the need to reassess economic and social conditions to better forecast electricity demand and develop appropriate generation and transmission infrastructure. Many large power projects, particularly those relying on gas and coal, are behind schedule, making revisions necessary to ensure energy security.

For instance, PDP VIII approved 23 gas-fired power projects with a combined capacity of 30,424 MW by 2030. However, only one plant, O Mon 1, is operational, and another, Nhon Trach 3 and 4, is 92% complete and expected to be commissioned in May 2025. Other major projects, such as the Lot B and Blue Whale gas projects, as well as plants like Hiep Phuoc 1, Ca Na, and Nghi Son, are still in the early stages of contracting, financing, or   investor  selection

The MoIT notes that, with the exception of Nhon Trach 3 and 4, most gas projects are unlikely to be completed before 2030 unless significant obstacles to LNG infrastructure development are overcome. This raises concerns about a large power supply shortfall between 2026 and 2030, particularly in northern Vietnam, posing risks to energy security.

Regarding coal power, the plan envisions 3,380 MW of new coal-fired capacity by 2030, after which coal development will be phased out in line with environmental commitments. However, five coal projects are behind schedule due to issues with shareholder changes and financing, including the 600 MW Cong Thanh, 1,200 MW Nam Dinh I, 1,320 MW Quang Tri, 1,980 MW Vinh Tan III, and 2,120 MW Song Hau II plants. These projects face opposition from local governments and financial institutions due to environmental concerns, making coal expansion less feasible.

Hydropower development also faces challenges, as the capacity available for new projects is limited, increasing the risk of setbacks.

For renewable energy, particularly wind power, achieving the planned capacity is proving difficult. Both onshore and nearshore wind projects were planned for a combined 21,880 MW, while offshore wind projects were projected at 6,000 MW. Solar power capacity is also being reassessed to bring it into line with actual conditions.

Given the delays in major power projects (coal, gas), the MoIT suggests expanding centralized solar power projects, which can be developed quickly to meet future electricity demand. The current plan includes 12,836 MW of centralized solar capacity, increasing to 168,594-189,294 MW by 2050. However, only 1,500 MW of additional solar power is planned through 2030.

Other power sources may also be prioritized in the revised plan. For example, biomass and waste-to-energy projects were allocated 2,270 MW by 2030 in the original plan, but many localities are proposing to expand these projects to help address environmental issues. The Ministry believes these energy sources should be prioritized for stronger development.

In addition, pumped-storage hydropower, battery storage, and electricity imports from Laos are seen as essential to meeting future energy demand and mitigating the risk of shortages.

RELATED NEWS
TAG: vietnam PDP VIII vietnam power supply vietnam energy plan
Other news
14:06, 2024/11/20
Hanoi strengthens export competitiveness and trade protection measures
Hanoi will work with the Ministry of Industry and Trade to ensure that businesses and manufacturers are ready for new challenges.
10:49, 2024/11/16
US reiterates Vietnam is not manipulating currency
The US Treasury Department’s positive evaluation underscores Vietnam’s progress in balancing its economic and monetary policies while fostering strong bilateral relations with the US.
21:14, 2024/10/31
Vietnam, Brazil: Building bridges through shared history and new partnerships
Vietnam and Brazil are forging a future of mutual development, bridging continents through their shared history and new partnerships.
16:54, 2024/10/29
Hanoi to attract tourists by showcasing local specialties at wholesale markets
Hanoi aims to enhance supervision of food safety and traceability, along with promoting cashless transactions.
16:28, 2024/10/27
National E-commerce Week, Vietnam Online Shopping Day 2024 set to kick off
This year's event will focus on celebrating and raising the status of Vietnamese products, according to the Ministry of Industry and Trade.
18:39, 2024/10/21
Vietnamese goods in rising demand among Hanoi residents
The domestic market, estimated to be worth US$180 billion and projected to grow to US$350 billion by 2025, presents an opportunity for Vietnamese goods to gain a foothold domestically.