Capital sky train project lags behind schedule
10:56, 2014/11/22
The Ha Noi urban sky train project is not likely to be completed before its December 31, 2015 deadline, the Railway Project Management Board admitted.
![](https://media.hanoitimes.vn/2021/05/14/logo_hntimes.png)
So far, only 320, or 76 per cent, of the project's pedestal footings, as well as seven foundations for its 12 train stations and 336 of 806 concrete blocks, have been assembled and completed.
![](http://cdn.hanoitimes.com.vn/mfiles/data/2014/11/81E08B23/1-5.jpg)
The 19 households at the site where the future Cat Linh station will be located have yet to agree on compensation settlement.
This alone has put the construction of the Cat Linh station seven months behind schedule, and it will take up to a year to finish the building after the site is cleared.
The Cat Linh-Ha Dong urban sky train project was approved in 2008 with a total investment of US$552 million. This was readjusted to $892 million, a 61.5 per cent surge, last April.
The construction phase is supposed to be completed at the end of December 2015, and the trial phase is supposed to begin in January 2016, said Nguyen Manh Hung, acting director general of the Railway Project Management Board.
Construction will have to be completed after the deadline that Deputy Prime Minister Hoang Trung Hai and Transport Minister Dinh La Thang set for the project. Hai and Thang expected the trial phase to begin in October 2015 and commercial activities to commence two months later, in December.
At a recent working session, the transport minister ordered project contractors to step up efforts to address issues that hindered construction speed and submit a progress report to the ministry for review.
The board must also prepare a detailed report on what project categories require cost adjustments, along with the specific reasons, Thang added.
A steel beam dropped from a crane on November 6 on the Cat Linh-Ha Dong urban railway project, killing one person and seriously injured two others.
This alone has put the construction of the Cat Linh station seven months behind schedule, and it will take up to a year to finish the building after the site is cleared.
The Cat Linh-Ha Dong urban sky train project was approved in 2008 with a total investment of US$552 million. This was readjusted to $892 million, a 61.5 per cent surge, last April.
The construction phase is supposed to be completed at the end of December 2015, and the trial phase is supposed to begin in January 2016, said Nguyen Manh Hung, acting director general of the Railway Project Management Board.
Construction will have to be completed after the deadline that Deputy Prime Minister Hoang Trung Hai and Transport Minister Dinh La Thang set for the project. Hai and Thang expected the trial phase to begin in October 2015 and commercial activities to commence two months later, in December.
At a recent working session, the transport minister ordered project contractors to step up efforts to address issues that hindered construction speed and submit a progress report to the ministry for review.
The board must also prepare a detailed report on what project categories require cost adjustments, along with the specific reasons, Thang added.
A steel beam dropped from a crane on November 6 on the Cat Linh-Ha Dong urban railway project, killing one person and seriously injured two others.
![](https://media.hanoitimes.vn/thumb_x138x92/2025/02/06/to_lich_river_1.jpg)
21:16, 2025/02/06
Reviving To Lich River: Replenishing water from Red River and West lakes
Taking the water from the Red River and the West Lake to clean To Lich River is just one piece of the puzzle. Drastic actions are needed to keep the environment clean and green.
![](https://media.hanoitimes.vn/thumb_x138x92/2025/01/30/1urenco.jpeg)
18:38, 2025/01/30
Urenco strives for a cleaner environment in Hanoi
Innovation in garbage collection vehicles is an important step in ensuring environmental sanitation, contributing to building a civilized, clean and beautiful urban area in a sustainable direction.
![](https://media.hanoitimes.vn/thumb_x138x92/2025/01/24/1dan_phuong.jpg)
09:55, 2025/01/26
Hanoi promotes urban decorations for Tet
The "Bright - Green - Clean - Beautiful" movement demonstrates Hanoi's unwavering commitment to sustainable development and environmental protection.
![](https://media.hanoitimes.vn/thumb_x138x92/2025/01/15/1thanh_hai.jpg)
22:21, 2025/01/15
Hanoi to increase supply of essential goods by 30%-35% for Tet
Authorities in Hanoi planned to prevent price hikes during the national holiday by stocking up on goods and ensuring food supplies.
![](https://media.hanoitimes.vn/thumb_x138x92/2025/01/01/bithu1.jpg)
22:39, 2025/01/01
Hanoi works to ensure merry Tet
The move aims to make the best preparations for the traditional Tet celebrations.
![](https://media.hanoitimes.vn/thumb_x138x92/2024/12/29/1ocop.jpeg)
17:37, 2024/12/30
Channel needed to expand Hanoi's OCOP products: Experts
Hanoi has devised a plan to boost the sale of OCOP products by creating OCOP venues associated with rural tourism and craft village visits in the city.
- Rising Like Bamboo: Vietnamese Identity on the Global Stage
- Circular economy requires solid waste management in Hanoi
- Hanoi's top priority is to keep students safe while traveling
- Hanoi pioneers in using interoperable smart cards for public transport
- Hanoi to establish customer service hub for administrative reform
- Hanoi tops country for blood donation in 2024