Work on Long Thanh airport passenger terminal to start in 2022
Phi Nhat 16:17, 2021/04/20
Dong Nai has been mapping out resettlement scheme to move people out of the project area.

Construction of the Long Thanh airport passenger terminal will kick off in early 2022.

The information was released by the Airports Corporation of Vietnam (ACV) at the meeting with the Ministry of Transport on April 19. ACV, the investor of the phase-one Long Thanh airport project, is conducting removal of unexploded ordnance and erect fence until September.

 Perspective of the Long Thanh international airport project. Photo: ACV

The ACV has proposed leaders of the southern province of Dong Nai to continue keeping watch of the ground during the execution of the project.  

Addressing the meeting, Deputy Minister of Transport Le Anh Tuan said that the Long Thanh airport is a breakthrough project of the transport industry in the 2021-25 period. Therefore, the related sides should ensure the disbursement progress of the project.

He required to draw up appropriate compensation, support and resettlement policies. “The building of airport fence should avoid flooding and blocking roads,” Tuan said.

Cao Tien Dung, Chairman of Dong Nai Provincial People's Committee, said the province is carrying out site clearance and it is expected that the entire 5,000ha area will be handed over to the investor in June. Dong Nai is mapping out resettlement scheme to move people out of the project area.

In January, the construction of the first phase of the Long Thanh Airport was kicked off, with an estimated investment of more than VND109 trillion (US$4.6 billion). 

The 5,500-ha airport will be built in three phases and is expected to have four runways and four passenger terminals to ensure a capacity of 100 million passengers and five million tons of cargo per year by 2040. Once fully operational, it will become a major international aviation hub in the region.

RELATED NEWS
TAG: Long Thanh International Airport ACV
Other news
22:24, 2024/04/22
Vietnam starts construction of US$432 million expressway to China
The expressway will stimulate socio-economic development in four major economic zones in Vietnam: the northern, central, southern, and Mekong Delta regions.
20:05, 2023/09/13
KOICA launches new training program for Vietnamese journalists
The program is well designed and attached to new trends in South Korea and the world, which can be applied in Vietnam.
17:55, 2023/03/27
UK-funded CFA to support nine low-carbon projects in Vietnam
The CFA is part of the UK Government's efforts to help Vietnam meet the commitments made by Prime Minister Pham Minh Chinh at COP26 in Glasgow in 2021.
16:17, 2022/03/10
Hanoi’s latest proposal on Ring road No.4 project to save US$380 million
The project, estimated to be around VND87.1 trillion (US$3.81 billion), would be divided into seven sub-components and carried out under the combination of private-public partnership (PPP) and public investment mechanisms.
18:30, 2022/02/10
Construction of $120-million compostable resin factory kicks off in Hai Phong
The project, invested by An Phat Holdings, is considered the largest green materials factory in Southeast Asia.
16:51, 2022/02/06
Construction of Long Thanh International Airport must be accelerated: Prime Minister
With such sluggish construction progress, Long Thanh International Airport may not be able to become operational by 2025 as planned.