ODA-funded projects for Vietnam encounter barriers
Payment and site clearance delay are major barriers to official development assistance (ODA)-funded projects in Vietnam, chief representative of the Japan International Cooperation Agency (JICA) in Vietnam Fujita Yasuo told at the yesterday`s press conference in Hanoi.
In the first half of the fiscal year 2017 from April 1 – September 30, Japanese ODA-funded projects brought fruits to Vietnam, mostly in the three pillars of promoting growth and competitiveness, coping with vulnerable issues and strengthening governance. Among them are a north-south highway and a project to transfer vaccine production technology to Vietnam’s State-run POLYVAC company.
Procurement data also showed that Vietnamese firms won numerous contracts via ODA projects. Yasuo said JICA highly values the Vietnamese government’s efforts to limit public debts, adding that ODA disbursement is not a major factor to increase public debts.
JICA suggests the Vietnamese government continue reviewing procedures to promptly decide on budget allocation for projects using loans, he said.
In the near future, JICA will continue working more closely with the Vietnamese government to discuss how to effectively devise and carry out priority projects, use capital from the private sector and Japanese firms.
During the six-month period, Japan committed nearly 61.8 billion JPY worth of ODA to new projects, 51.2 billion USD of which was disbursed. A project using non-refundable aid worth 1.8 billion JPY was also signed.
15:58, 2023/10/18
Japan gives Vietnam biggest-ever ODA package
The focus of the financial support is infrastructure, manpower, and post-pandemic economic recovery.
15:45, 2023/10/18
Japan gives Vietnam biggest-ever ODA package
The focus of the financial support is infrastructure, manpower, and post-pandemic economic recovery.
20:59, 2023/07/05
Japan provides US$422 million ODA loans to Vietnam
The loans enable Vietnam to boost its recovery strategies adopted by the National Assembly in early 2022.
16:49, 2023/04/16
Prime Minister calls for Metro No. 1 project to be completed by September
Completion of the Metro No. 1 project is scheduled for the fourth quarter of 2023, after 12 years of construction.
15:57, 2021/10/23
70% highway road in Vietnam built with Japan loans
Infrastructure projects help smooth economic connectivity among parts of Vietnam and between the country and other ASEAN nations.
05:26, 2019/10/23
Vietnam should be cautious about environmental impact investment: JICA
Inflows from emerging countries might fail to meet environmental protection requirements.
- Japan’s ODA to Vietnam to focus on issues of global concerns from 2020: JICA
- Private sector investment finance – JICA’s tool to seek investment in infrastructure
- Vietnam tops priority of Japanese infrastructure investment
- Hanoi eager to quicken railway projects's pace
- Belgium helps Vietnam to respond to climate change
- PM urges report on Ho Chi Minh City's two key metro lines