Hanoi metro rail gets fresh loans
17:54, 2015/11/23
Additional loan agreements have been signed for the Hanoi train station-Nhon urban metro rail project, announced Nguyen Quang Manh, Director of the project`s management board at a recent meeting with the Ministry of Transport.

The project had initially received investment capital of 783 million EUR (733 million USD). However, after several years of construction, this investment capital has been adjusted to more than 1.17 billion EUR (1.09 billion USD), an increase of nearly 400 million EUR (374 million USD).
Therefore, the board has signed the additional loan agreements with sponsors to get more money for the project, Manh said, adding that the concerned ministries are obliged to report the increase in the project's investment capital to the Government.
According to representatives of the sponsors, the slow progress of site clearance might be among the reasons for the situation.
Deputy Minister of Transport Nguyen Hong Truong said site clearance and arrangements for resettlement are very difficult as the urban railway passes most of the city's residential areas. Therefore, sponsors should consider the problem carefully and handle it properly.
Until the adjustment in investment capital is verified, the Nam Thang Long-Tran Hung Dao urban railway has been asked to pause construction.
The project was approved in 2008, and construction began in December 2013, with an estimated investment capital of 19.5 trillion VND (858 million USD). However, the project has yet to be implemented, as it is still awaiting approval for the increase in its investment capital to 51.7 trillion VND (2.2 billion USD) from the Ministry of Planning and Investment.
Manh said the delay in receiving the ministry's approval has prevented the project from finding financial sources. By the end of next year, the loan agreement with JICA, the main sponsor of the project, will expire.
He added the Ministry of Planning and Investment has hired a consulting firm to evaluate the projects and plans to release the official report on the situation next April.
Therefore, the board has signed the additional loan agreements with sponsors to get more money for the project, Manh said, adding that the concerned ministries are obliged to report the increase in the project's investment capital to the Government.
According to representatives of the sponsors, the slow progress of site clearance might be among the reasons for the situation.
Deputy Minister of Transport Nguyen Hong Truong said site clearance and arrangements for resettlement are very difficult as the urban railway passes most of the city's residential areas. Therefore, sponsors should consider the problem carefully and handle it properly.
Until the adjustment in investment capital is verified, the Nam Thang Long-Tran Hung Dao urban railway has been asked to pause construction.
![]() Construction site of the Hanoi train station - Nhon urban metro rail project in Cau Giay district
|
Manh said the delay in receiving the ministry's approval has prevented the project from finding financial sources. By the end of next year, the loan agreement with JICA, the main sponsor of the project, will expire.
He added the Ministry of Planning and Investment has hired a consulting firm to evaluate the projects and plans to release the official report on the situation next April.

12:17, 2025/02/25
Vietnam eyes top 3 in investment environment in ASEAN next 2 years: Party Chief
A key objective is to trim off at least 30% of administrative procedures and cut both business costs and unofficial fees.

18:03, 2025/02/22
Vietnam attracts South Korean tech investment at SEMICON Korea 2025
The event provided a platform for Vietnam to showcase its semiconductor potential and reaffirm its commitment to developing high-tech industries and strengthening international cooperation.

16:46, 2025/02/20
Swedish group plans US$1 billion investment in Binh Dinh recycling plant
By creating a large number of jobs and promoting a green economy, the initiative is important in establishing Vietnam as a global hub for the circular textile sector.

10:52, 2025/02/13
Samsung plans to invest in AI, semiconductors in Vietnam
Vietnam will continue improving its investment environment and driving strategic breakthroughs in order to usher in a new era of economic development.

17:20, 2025/02/07
Vietnam's data center construction costs among the lowest in Asia Pacific
The country has a lot of potential to become one of the most important data markets in the region.

21:05, 2025/02/03
Bright prospects for FDI inflows into Vietnam in 2025
Market size, growth potential, low labor costs, and stable political and social conditions continue to be Vietnam’s selling points in attracting foreign investors.
- Foreign companies confirm investment expansion in Vietnam in 2025
- PM invites Skoda to manufacture electric vehicles in Vietnam
- US Berggruen Holdings to help Vietnam set up investment funds
- Vietnam releases Esports White Book 2022-2023
- Aircraft manufacturer Embraer seeks comprehensive aviation partnership with Vietnam
- Better links with FDI firms to support Hanoi businesses