Auditors find financial infringements at Hanoi’s first metro project
The project’s total investment ballooned by 205%, from the original estimate of some VND8.7 trillion (US$552.8 million) to more than VND18 trillion (US$868 million).
The State Audit of Vietnam (SAV) has uncovered several infringements of financial regulations and improper payments at the Cat Linh-Ha Dong urban railway project in Hanoi, which has seen delays, local media reported.
The SAV, under the National Assembly, recently announced the results of its audits of the construction, management and use of investment capital in the railway project, where the main contractor is China Railway Sixth Group Co. Ltd.
The auditors found several financial regulation violations in the planning, appraisal and approval of its investment and capital increase, and the signing of the project’s contracts.
The project’s total investment ballooned by 205%, from the original estimate of some VND8.7 trillion (US$552.8 million) to more than VND18 trillion (US$868 million), including VND13.8 trillion, or US$670 million, in loans from China.
The SAV pointed out that the Railway Projects Management Board improperly spent VND91 billion (US$3.9 million) when the project was set up. Other VND14 billion (US$602,000) was also found unjustified at the management board of investment for construction of civil and industrial architectural projects of Hanoi. Both boards are asked to refund the inappropriate expenditure.
When it comes to the efficiency of the project, the SAV concluded that the investor failed to calculated operational costs. Therefore, the SAV said it was inaccurate for them to claim the project was commercially viable.
The unit was also responsible for determining the liability of consulting units that had made mistakes.
The SAV requested the Ministry of Transport to keep a close watch on its public investment and identify the responsibilities of individuals and organizations in the unlawful approval of the upward revision of the project’s investment.
Therefore, the SAV asked the investor to reduce the payment by VND175 billion (US$7.525 million) to the contractors as well as to negotiate with the general contractor to cut the payment by VND428 billion (US$ 18.4 million).
Besides, the SAV also revised down the declared management expenses, commitment fee, principal and interests by VND269 billion (US$11.567 million).
The auditing agency also proposed to handle collective and individual responsibilities in approving the total investment amount adjustments and improper bidding approval of Chinese investors.
Hanoi reports to the government on the project
Hanoi’s authority will report difficulties for the inauguration of the Cat Linh - Ha Dong urban railway project to the Vietnamese government and seek its instructions.
In early September, the Hanoi Party Committee made public the progress of the Cat Linh - Ha Dong urban railway project. Accordingly, Hanoi city has discussed with the Ministry of Transport about the handover of the railway to Hanoi’s administration.
However, due to some technical issues, registration, acceptance and taking over, which have not been agreed between the Ministry of Transport and the project’s general contractor, thus, the transfer of metro line has been continuously delayed, the report said.
The SAV, under the National Assembly, recently announced the results of its audits of the construction, management and use of investment capital in the railway project, where the main contractor is China Railway Sixth Group Co. Ltd.
A train test runs on the Cat Linh-Ha Dong urban railway in downtown Hanoi. Photo: TNO
|
The project’s total investment ballooned by 205%, from the original estimate of some VND8.7 trillion (US$552.8 million) to more than VND18 trillion (US$868 million), including VND13.8 trillion, or US$670 million, in loans from China.
The SAV pointed out that the Railway Projects Management Board improperly spent VND91 billion (US$3.9 million) when the project was set up. Other VND14 billion (US$602,000) was also found unjustified at the management board of investment for construction of civil and industrial architectural projects of Hanoi. Both boards are asked to refund the inappropriate expenditure.
When it comes to the efficiency of the project, the SAV concluded that the investor failed to calculated operational costs. Therefore, the SAV said it was inaccurate for them to claim the project was commercially viable.
The unit was also responsible for determining the liability of consulting units that had made mistakes.
The SAV requested the Ministry of Transport to keep a close watch on its public investment and identify the responsibilities of individuals and organizations in the unlawful approval of the upward revision of the project’s investment.
Therefore, the SAV asked the investor to reduce the payment by VND175 billion (US$7.525 million) to the contractors as well as to negotiate with the general contractor to cut the payment by VND428 billion (US$ 18.4 million).
Besides, the SAV also revised down the declared management expenses, commitment fee, principal and interests by VND269 billion (US$11.567 million).
The auditing agency also proposed to handle collective and individual responsibilities in approving the total investment amount adjustments and improper bidding approval of Chinese investors.
Hanoi reports to the government on the project
Hanoi’s authority will report difficulties for the inauguration of the Cat Linh - Ha Dong urban railway project to the Vietnamese government and seek its instructions.
In early September, the Hanoi Party Committee made public the progress of the Cat Linh - Ha Dong urban railway project. Accordingly, Hanoi city has discussed with the Ministry of Transport about the handover of the railway to Hanoi’s administration.
However, due to some technical issues, registration, acceptance and taking over, which have not been agreed between the Ministry of Transport and the project’s general contractor, thus, the transfer of metro line has been continuously delayed, the report said.
21:04, 2024/11/27
Hanoi aims to use 100% LED street lighting by 2025
The LED fixtures are expected to help reduce the cost of lighting Hanoi's streets.
20:59, 2024/11/27
Hanoi's Pho declared national intangible heritage
Pho Hanoi, now a National Intangible Cultural Heritage, will be the centerpiece of a year-end festival celebrating its timeless inheritance and cultural significance.
15:39, 2024/11/27
European designer's silk outfit debuts at Hanoi festival
This year, Barbara Ebbli, founder of the Italian fashion brand Malaika, worked with the Hanoi Coordination Office to consult on designs using Vietnamese silk.
15:31, 2024/11/27
Hanoi, Xinjiang explore tourism cooperation
Hanoi will strengthen its ties with Xinjiang and encourage broader collaboration between Xinjiang and other provinces in Vietnam and across Southeast Asia.
16:34, 2024/11/26
Hanoi, Beijing strengthen cooperation in labor union development
Cooperation between the two sides would foster mutual learning and labor movements and trade union activities in both countries.
21:16, 2024/11/25
Hanoi seeks investment from China's Guangdong enterprises
Following the signing of a memorandum of understanding in 2023, the two sides have strengthened their cooperation.
- Hanoi to expand underground space by 2030
- Hanoi accelerates three major bridge projects in 2025
- Hanoi's largest wastewater treatment plant to start trial run in early December
- Hanoi to lead national digital transformation efforts
- Highly received by local passengers, e-ticketing shows Hanoi on the way to become a smart city
- Hanoi commends outstanding individuals in vocational education