Hanoi’s mayor urges speedy progress in Ring road No.4 project
Chairman of Hanoi People's Committee Tran Sy Thanh has urged State agencies to leave the festive spirit behind and start working without delay. The leaders of each agency must take responsibility for performing their duties in reaching objectives.
14:32, 2023/02/11
Hanoi sets up Steering Committee for Ring road No.4 project
The committee is tasked with ensuring the project’s completion on time and to a high standard.
12:08, 2023/02/08
Ring Road No.4 project on track to start construction in June
The project, with an investment capital of VND86 trillion (US$3.7 billion), is expected to be operational by 2028.
16:35, 2022/11/25
Hanoi to kick start Ring Road No.4 construction next June: City Party chief
The project, once completed, will have a great impact on the social development not only of Hanoi but also of the provinces and cities in the Capital Zone.
16:54, 2022/11/08
Construction of Ring Road No.4 must advance daily: Hanoi Mayor
The mayor called on all city units to speed up the preparation of projects, especially site clearance and land compensation for affected households.
15:12, 2022/10/24
Hanoi speeds up Ring road No.4 project
Hanoi's authorities expect to complete the delimitation of the project area before November 15, paving the way for the site clearance.
10:19, 2022/09/23
Hanoi identifies site clearance as priority for Ring road No.4 project
Hanoi would need at least 741 hectares of clear sites for the project, covering areas in seven districts.
17:12, 2022/09/16
Hanoi announces action plan on Ring-road No.4 implementation
The action plan set the timeline until the end of September 2022 for the authorities of three provinces/cities of Hanoi, Hung Yen, and Bac Ninh to set up a Steering Committee to oversee the project implementation.
08:30, 2022/09/12
Ring road No.4 offers Hanoi chances for economic breakthroughs
The project holds significant meaning for socio-economic development in Hanoi and the country overall.
14:47, 2022/08/19
Construction of the No.4 ring road to kick off in mid-2023
The aim is to ensure the completion of the ring road by 2026 and to put it into operation from 2027.