Runway upgrade at Vietnam's 2 busiest airports must be finished before year-end
Nhat Minh 08:50, 2020/11/02
The first phase of the two runway upgrade projects of Noi Bai and Tan Son Nhat airports are expected to be completed by the end of 2020, and become operational in early 2021.

Permanent Deputy Prime Minister Truong Hoa Binh has urged contractors to finish the upgrade of the runways at Noi Bai and Tan Son Nhat airports and put them into operation before the year-end, the peak travel season, local media reported.

 Noi Bai International Airport is in the process of upgrading. Photo: VNA

Despite facing many difficulties in 2020, the government still earmarks resources for transport infrastructure development, including the aviation industry, Mr. Binh said when inspecting the implementation progress of the projects on October 31. 

The development of transport infrastructure plays a vital role in economic development and has spill-over effects on other industries, he added.  

As the projects are facing capital shortage, Mr. Binh asked the Ministry of Planning and Investment to arrange funding by adjusting the medium- and long-term capital plan or transferring capital from projects with slow disbursement.

So far, the workload of the runway 1B upgrade at Noi Bai airport in Hanoi has been 75% completed and is expected to finish by December 31. The repair of taxiways and other items are being sped up, according to Mr. Duong Viet Roan, director of Thang Long Project Management Board.

At Tan Son Nhat International Airport, the project upgrading the 25R /07L runway and other taxiways would be completed before December 10 and become operational before December 31.

Regarding the handover of cleared site for the construction of terminal T3 at Tan Son Nhat airport, the deputy prime minister asked the Ministry of Defense to accelerate the review of the land fund in Tan Son Nhat area, soon plan to hand over the site to Airports Corporation of Vietnam for the implementation of the T3 passenger terminal construction project. 

The two projects to repair Tan Son Nhat and Noi Bai runways kicked start on June 29 with an estimated cost of VND4.05 trillion (roughly US$174 million), equally distributed to the two. The upgrade will be carried out in two phases, with the first lasting 6 months and the second 14 months. 

RELATED NEWS
TAG: Noi Bai Tan Son Nhat airports ACV
Other news
20:33, 2021/33/11
State-run cement producer VICEM posts annual increase of US$30 million in profit
The company sets a revenue target of over VND35 trillion (US$1.5 billion) in 2021, up 7% year-on-year, and pre-tax profit of VND2.3 trillion (US$99 million), or an increase of 13%.
22:48, 2021/48/03
Work starts on Long Thanh International Airport construction on January 5
The Long Thanh International Airport is expected to reduce the load on Tan Son Nhat International Airport in Ho Chi Minh City.
14:15, 2020/15/31
The interchange spanning Hanoi–Hai Phong expressway on track to completion
The Hanoi's key road project worth US$17.3 million is expected to be operational on January 10, 2021, two months ahead of schedule.
06:11, 2020/11/05
Proper construction planning – a long term solution to air pollution
The Hanoitimes Urbanisation has helped push up Hanoi’s economic growth. Yet the lack of synchronous solutions may bring about various problems for the city including environmental pollution.
16:27, 2020/27/03
Vietnam accelerates implementation of four major ODA transportation projects
The disbursed amount of official development assistance (ODA) funds in Vietnam in the first nine months of 2020 stood at only VND26 trillion (US$1.12 billion), equivalent to 32.43% of the year’s estimate.
08:50, 2020/50/02
Runway upgrade at Vietnam's 2 busiest airports must be finished before year-end
The first phase of the two runway upgrade projects of Noi Bai and Tan Son Nhat airports are expected to be completed by the end of 2020, and become operational in early 2021.