Hanoi’s ODA disbursement meets 30% of target in H1
Ngoc Thuy - Nha Trang 18:39, 2020/06/25
Hanoi has been implementing a number of measures since the beginning of the year to speed up disbursement of public investment funds, including ODA sources, said a Hanoi leader.

As of end-June, the Hanoi city government has disbursed VND1.55 trillion (US$66.35 million) worth of official development assistance (ODA) loans, meeting 29.7% of the year's target, according to the city's deputy mayor Nguyen Doan Toan.

 Vice Chairman of the Hanoi People's Committee Nguyen Doan Toan.

In 2020, the government allowed Hanoi to disburse VND40.67 trillion (US$1.74 billion) for capital expenditure, of which VND3.29 trillion (US$140.82 million) came from ODA loans, Toan informed a conference on June 25.

In May, Hanoi adjusted the investment plan and revised the capital expenditure target to VND44.91 trillion (US$1.92 billion). Of the amount, the city disbursed VND8.12 trillion (US$347.52 million) in the first five months, or 18.1% of the total.

To speed up disbursement of public investment funds, including ODA, Hanoi has been implementing a number of measures since the beginning of the year, including a review of the existing legislation, specifying responsibilities of local agencies, among others, Toan said.

Toan, however, points out some difficulties in implementing a number of ODA-funded projects, such as the Nam Thang Long–Tran Hung Dao section of urban railway line No.2, which requires additional capital, and the unfinished planning of underground station C9 near Hoan Kiem Lake.

Additionally, the Nhon – Hanoi Station section of this urban railway project faces obstacle in advanced payment procedures for package No.9, Toan said, attributing the issue to the ongoing negotiations on an additional loan of EUR20 million (US$22.44 million) from the French government.

Public investment is considered Hanoi’s top priority to ensure economic recovery in the post Covid-19 pandemic.

Hanoi's Party chief Vuong Dinh Hue suggested that the city should set up a tasks force with the aim of speeding up the disbursement progress, and each process must be tied to individuals' responsibility.

RELATED NEWS
TAG: Hanoi Vietnam Public investment ODA covid-19 coronavirus nCoV pandemic economic recovery
Other news
17:45, 2020/45/07
Hanoi finds another positive coronavirus case linked to Danang
Hanoi's new Covid-19 patient has self-isolated at home since July 27.
15:37, 2020/37/07
Hanoi to host cultural events to mark 1010th anniversary of its foundation
A solemn celebration, themed “Thang Long-Hanoi, Eternal Vitality” is expected to take place on October 10.
15:05, 2020/05/07
Hanoi runs RT-PCR test on nearly 100,000 returnees from Danang
The RT-PCR test is totally reliable while the accuracy of Covid-19 quick test is only from 60% to 75%.
00:42, 2020/42/07
Negative coronavirus rapid test results still imply transmission risk: Hanoi mayor
The Hanoi mayor said that though the 72,000 people were tested quickly and got negative results, there is a strong probability of undetected Covid-19 infection.
19:23, 2020/23/06
Hanoi to call for EU investment in pharmaceutical and hi-tech industries: Mayor
The EVFTA is an opportunity for Hanoi to boost cooperation in trade and investment with EU member countries, said Hanoi’s mayor Nguyen Duc Chung.
12:58, 2020/58/06
800 Hanoian returnees from Danang to undergo concentrated quarantine
The returnees must undergo concentrated quarantine for having a long stay in Danang and bearing high risk of infection.