Drastic measures needed to realize disbursement target of public funds
Ngoc Thuy - Thao Nguyen 15:33, 2020/09/21
As the disbursed amount between January and August was equivalent to 50.7% of the target, the government is under pressure to spend the remaining 50% in the remaining four months.

Despite improvements in disbursement of public funds, the progress remains slower than expected and requires huge efforts to meet the government target by year-end.

 Drastic measurse are required for Vietnam to realize the disbursement target of public funds this year. Photo: Thanh Hai. 

In the first eight months of 2020, the disbursed amount of public investment stood at VND250 trillion (US$10.8 billion), up 30.4% year-on-year but equivalent to only 50.7% of the target.

The government, therefore, is under pressure to expend the remaining 50% of public investment funds in the remaining four months.

As of present, the disbursement progress lies on the implementation of major infrastructure projects, including the Eastern North-South expressway project, Long Thanh International Airport, or the upgrade of runways of international airports of Tan Son Nhat and Noi Bai, among others.

Meanwhile, projects financed by the official development assistance (ODA) fund such as the Ben Luc – Long Thanh expressway and urban railways are lagging behind schedule, resulting in a low disbursement rate.

Minister of Planning and Investment Nguyen Chi Dung attributed the slow disbursement to changes in policies, difficulties in site clearance, as well as lack of capabilities from project owners and contractors.

Regarding ODA projects, Mr. Dung said many are lacking legal grounds to start construction works, mainly due to adjustments to the financing agreements and investment procedures.

Mr. Dung added the Covid-19 pandemic has also impacted foreign-invested projects, specifically in importing equipment, machinery, and the entry of foreign experts.

Amid mounting difficulties, Prime Minister Nguyen Xuan Phuc has reiterated the government’s determination to fully disburse entirely the target amount of public funds, adding this is key to boost economic growth during the Covid-19 crisis.

In a meeting late August, Mr. Phuc warned officials would face disciplinary actions if their ministries and localities fail to realize their respective disbursement targets of public investment funds for this year,

On this issue, Minister of Planning and Investment Dung also said the government is willing to transfer state capital from projects whose disbursement is lagging behind those with faster pace.

Among measures to boost the disbursement performance, Mr. Dung said both central and local governments would hold monthly meetings to address related issues.

In a meeting with the ADB’s Country Director to Vietnam Andrew Jeffries on September 17, PM Phuc requested the bank’s support in disbursing US$900 million to ADB-funded projects in 2020.

RELATED NEWS
TAG: Vietnam disbursement covid-19 coronavirus nCoV pandemic MPI Public investment
Other news
20:33, 2021/33/11
State-run cement producer VICEM posts annual increase of US$30 million in profit
The company sets a revenue target of over VND35 trillion (US$1.5 billion) in 2021, up 7% year-on-year, and pre-tax profit of VND2.3 trillion (US$99 million), or an increase of 13%.
22:48, 2021/48/03
Work starts on Long Thanh International Airport construction on January 5
The Long Thanh International Airport is expected to reduce the load on Tan Son Nhat International Airport in Ho Chi Minh City.
14:15, 2020/15/31
The interchange spanning Hanoi–Hai Phong expressway on track to completion
The Hanoi's key road project worth US$17.3 million is expected to be operational on January 10, 2021, two months ahead of schedule.
06:11, 2020/11/05
Proper construction planning – a long term solution to air pollution
The Hanoitimes Urbanisation has helped push up Hanoi’s economic growth. Yet the lack of synchronous solutions may bring about various problems for the city including environmental pollution.
16:27, 2020/27/03
Vietnam accelerates implementation of four major ODA transportation projects
The disbursed amount of official development assistance (ODA) funds in Vietnam in the first nine months of 2020 stood at only VND26 trillion (US$1.12 billion), equivalent to 32.43% of the year’s estimate.
08:50, 2020/50/02
Runway upgrade at Vietnam's 2 busiest airports must be finished before year-end
The first phase of the two runway upgrade projects of Noi Bai and Tan Son Nhat airports are expected to be completed by the end of 2020, and become operational in early 2021.